The approval sets a timetable, not a bill of materials
A State Council executive meeting on 31 July 2026 approved four nuclear power projects. The projects named in reporting are Jinqimen Phase II in Zhejiang, Taipingling Phase III in Guangdong, Zhuanghe Phase I in Liaoning and Laiyang Phase I in Shandong, each with two units — eight units in total. The same reporting puts total investment above CNY 170 billion, a figure that should always be quoted as reported, not as an official release.
For a piping or fitting supplier, the approval means a pipeline of work that will reach procurement over the coming years. It does not mean an order, and the gap between the two is almost entirely made of specifications: which standards apply, which items are nuclear-grade, and which are conventional-island work.
What the figures can and cannot carry
| Item | Figure | Status |
|---|---|---|
| Projects approved | Four (Zhejiang, Guangdong, Liaoning, Shandong) | Reported |
| Units | Eight, two per project | Reported |
| Approval date | 31 July 2026 | State Council executive meeting |
| Total investment | Above CNY 170 billion | Reported estimate, quote with attribution |
| Reactor model per project | Not stated uniformly | Not to be inferred |
The last row is the one to watch in internal documents. Reports name projects and unit counts consistently, but reactor model and unit configuration are not given with the same uniformity, and a supplier should not construct a model list from press coverage. Where the model matters to the technical scope, it comes from the project's own documentation.
Which standards a conventional-island order cites
Two industry standards do most of the work on the conventional-island side.
DL/T 850-2023, pipe prefabrication for power stations, was issued on 11 October 2023 and took effect on 11 April 2024, replacing the 2004 edition; its scope states that prefabrication of steel steam and water piping in the conventional island of nuclear power stations may refer to it. That single sentence is what places conventional-island piping in the fossil-plant standards family rather than in the nuclear codes.
DL/T 695-2025, steel butt-welding fittings for power stations, was issued on 28 September 2025 and takes effect on 28 March 2026. It is the fittings standard for the same family of work.
A project order will cite these alongside the project's own specification, which fixes material, pressure class, welding and examination requirements. The standards give the framework; the project gives the numbers.
Where the boundary sits, and why to hold it
The boundary between conventional-island and nuclear-grade work is not a matter of degree. Nuclear-grade components are governed by a separate regulatory regime, with qualification, traceability and inspection requirements that do not follow from the industry standards above, and this article does not state what those requirements are.
For a supplier, holding the boundary means asking one question early: is the item in the nuclear island or the conventional island? An inquiry that does not answer it will be quoted either against the wrong standard family or with a scope exclusion that surprises the buyer later. Holding the boundary protects both sides — the supplier does not promise a qualification they do not hold, and the buyer does not assume a qualification that was never requested.
What to establish before quoting
- Island classification of each item, stated in the requisition.
- The design code and the standard editions the project adopts, with the date they apply from.
- Material and pressure class, from the project specification rather than from a similar plant.
- Prefabrication scope: spool drawings, welding and heat treatment, and who performs them.
- Examination and documentation: methods, extent and the records that follow the component.
Where a value is not yet fixed, leave it open and ask for the design basis. On a project of this scale the design basis exists; the only question is whether it has reached the requisition.
- Product family: power plant piping parts
- Prefabrication: prefabricated piping and installation
- Send the specification: inquiry
Sources
Butuh penawaran untuk produk yang disebutkan dalam artikel ini?
Kirim spesifikasi Anda dan tim perpipaan tekanan kami akan merespons dalam satu hari kerja.
Kirim RFQPenawaran 4 jam
Produk yang dibahas di artikel ini
Butuh penawaran? Kirim spesifikasi Anda dan tim perpipaan kami merespons dalam 4 jam kerja.
Bacaan terkait
Berita industriChina's 15th Five-Year Pipeline Plan: What 20,000 km of New Line Means for Fitting Demand
The 15th Five-Year Plan reported in August 2026 adds 20,000 km of oil and gas pipeline, with nearly 40 major projects already under construction. What the published figures do and do not tell a fitting buyer.
Berita industriManatee Gas FID in Trinidad and Tobago: A Source-Checked LNG Feedgas Update
Shell's July 2024 FID for the Manatee gas development in Trinidad and Tobago signals continued investment in LNG feedgas. This update outlines what is verified, what remains to be checked, and how EPC buyers can align procurement with evolving project timelines.
Berita industriHammerhead FID: Guyana's Seventh Offshore Development in the Official Record
ExxonMobil has taken FID on the Hammerhead project offshore Guyana, the seventh development on the Stabroek block. With a capacity of 150,000 bopd and a $6.8 billion investment, production is expected in 2029. This article outlines the key facts and procurement implications for piping suppliers.